Background
Trailer Bridge chartered two barges to Work Cat, which included a no-lien clause. Work Cat then chartered tugboats from Louisiana International Marine to tow the barges. Work Cat failed to pay LIM for towage services and filed for bankruptcy. LIM asserted a maritime lien against the barges. Trailer Bridge sued to declare the barges free of the lien, arguing the no-lien clause barred it and that LIM relied solely on Work Cat’s credit.
The court’s reasoning
The court applied the Commercial Instruments and Maritime Liens Act, which presumes charterer agents have authority to procure necessaries. The court found LIM provided towage, a statutory necessary, to a vessel. Trailer Bridge failed to prove LIM deliberately intended to look solely to Work Cat’s credit. Regarding the no-lien clause, the court held that actual knowledge must precede the agreement. LIM received the charter containing the clause after the tug charter was finalized, so the clause did not bar the lien. The court also affirmed the exclusion of fuel and lubricant costs from the lien value, as these were provided to the tug, not the barge.
Because LIM lacked actual knowledge of the no-lien provision at the time it contracted to provide towage services, a maritime lien attached to the barges.
Opinion at 2
What it means going forward
Suppliers of towage and other necessaries can enforce maritime liens against vessels even if a charter party contains a no-lien clause, provided the supplier did not have actual knowledge of that clause before the contract was executed.