EMCO CORPORATION v. ARMOR MACHINE & MANUFACTURING LTD
The Sixth Circuit affirmed a summary judgment ruling that a buyer breached a contract by refusing to accept a custom machine due to delivery delays. The court held that the contract explicitly defined delivery dates as estimates subject to the seller's discretion, meaning the delays did not constitute a substantial breach.